Rabbit Ridge Road Sign

CONSTRUCTION NOTICE: RABBIT RIDGE PHASE 2 CONSTRUCTION

Note: This entry was last modified on June 20, 2022: 4:06 pm and may be out of date.

PROJECT INFORMATION:

  • The second phase of Rabbit Ridge Paving Improvements is set to begin on June 23, 2022.
  • Time of construction is 270 calendar days with a completion date in March of 2023.
  • The improvements include a new 12-inch water line along the west ROW of the roadway and two new lanes of concrete.
  • The improvements will be located in the area from FM 550 to Lodge Hill.
  • The first work to be completed will be the new 12” water line.

BEGINNING IN LATE JULY OR EARLY AUGUST, RABBIT RIDGE TRAFFIC FLOW WILL BE DIVERTED ONEWAY FROM FM 550 NORTH TO LODGE HILL, FOR THE REMAINDER OF THE PROJECT.

The contractor is Ed Bell Construction Company, phone number: Mike Rieder (214) 358-6581 or email: Mike.Rieder@ebcc.com.

If you have any questions or concerns regarding the referenced project, please contact the city engineer, Richard Dormier, at 972-489-6523 or at his email: richard@fmi-dallas.com.