CITY OF HEATH CAPITAL IMPROVEMENT PLAN PROGRESS
Note: This entry was last modified on May 30, 2018: 11:04 am and may be out of date.
The Capital Improvement Plan continues to progress, providing upgrades and improvements to our City infrastructure.
COMPLETED PROJECTS
- Dennis Bailey Drive/Rabbit Ridge Phase 1 (adjacent to Ridge Lakes subdivision)
- Rabbit Ridge and Horizon Rd. Extension (Adjacent to Cobblestone Subdivision)
- Shepherds Glen Force Main and Gravity Sewer
- Woodbridge Lift Station
- Country Club Drive Rehabilitation
- Amy Parks Driveway (Towne Center Park)
- Stoneleigh Pedestrian Crossing
- Utilities Relocation for Next Phase of TxDOT FM-740 Widening
- Safe Routes to School Trails
- Buffalo Creek Trail Repair along Horizon Road
- New Lake Wall at Terry Park
- Multiple Utility Improvements to Facilitate Current and Future Residential and Commercial Development
- McDonald Rd. Improvements Phase 1 (FM-550 to Stoneleigh Subdivision Connection)
- 18 Streets included in the On-going Citywide Street Repair Program
- Towne Center Baseball Rehabilitation
- Jeff Boyd Waterline (12” water line extension along FM-549 and Jeff Boyd)
- Country Club Drive Paving and Drainage Repair
- CIP Street Repair Phase 2 – 11 Locations throughout the City
PROJECTS NOW UNDERWAY
- Rabbit Ridge Phase 2 (Ridge Lakes subdivision to FM-550 – Includes 12″ water Line) – Obtaining right-of-way; plans 85% complete.
- Myers/Crisp Roadway Improvements – The project is scheduled to begin in July. Construction time is estimated to be 7 to 9 months.
- Hubbard Drive Roadway Improvements (reconstruction of sections of Hubbard Drive, including drainage improvements, FM-740 to south Scenic Drive) – Engineering has started. Additional right-of-way will be needed for the project.
- 3 Million Gallon Ground Storage Tank and Pump Station Expansion – Construction has begun and will be completed February 2019.
- McDonald Road Phase 2 Roadway Project (Phase 1 to City Limits: Falcon Point Subdivision): Right-of-way is obtained. New right-of-way will reduce the amount of one-lane roadway during construction. Private utilities will have to be relocated before the project will be bid. Once started, construction time is estimated to be 6 to 7 months.