CIP Project Update – Dennis Bailey/Rabbit Ridge Phase 1

Project: The City is reconstructing a portion of Dennis Bailey and Rabbit Ridge. The project includes the reconstruction of Dennis Bailey from FM-549 to Rabbit Ridge and the section of Rabbit Ridge adjacent to the Ridge Lakes Addition (location map above). Start Date: The project is scheduled to begin July 5, 2016 and is weather […]

CIP Roadway Repair Project Phase 2 – Dunford Drive

Project: The City project includes reconstruction of a portion of  Dunford Drive near Normandy Lane. Start Date: Monday, May 23, 2016 (weather permitting) Completion Time: Approximately 2 week. Contractor Guidelines and Information: Construction is allowed between 7:00 am to 8:00 pm, Monday through Friday. The roadway will typically be constructed one-half at a time and […]

CIP Roadway Repair Update Phase 2 – Halford Drive

Project: The City project includes reconstruction of a portion of  Halford Drive at the intersection with Halford Ct. Start Date: Tuesday, May 17, 2016 (weather permitting) Completion Time: Approximately 2 week. Contractor Guidelines and Information: Construction is allowed between 7:00 am to 8:00 pm, Monday through Friday. The roadway will typically be constructed one-half at […]

CIP Roadway Repair Update – Phase 2

Project: The City project includes reconstruction of a portion of Stoneleigh Drive near Westchester Ct Start Date: Monday, April 18, 2016 (weather permitting) Completion Time: Approximately 1 week. Project: The City project includes reconstruction of a portion of Scenic Place Start Date: Wednesday, April 20, 2016 (weather permitting) Completion Time: Approximately 3 weeks. Project: The […]

CIP Update: James Drive Construction

The Capital Improvement Program Roadway Repair Project continues with the reconstruction of James Drive between Heath Drive and Chilton Point. The work is scheduled to begin Wednesday, March 23 and be conducted between 7 a.m. and 8 p.m. on weekdays. The roadway will be reconstructed one-half at time and be reduced to one lane during […]

CIP Update: Yankee Creek Construction

Phase 2 of the Capital Improvement Plan Street Repair Project is underway with the reconstruction of Yankee Creek from Rush Creek to Drew. Work is scheduled to begin Monday, February 29.One side of the street will be under construction at a time to allow traffic flow to continue. Access will be provided to homeowners along […]

TxDOT FM 740 Update

Progress can sometimes be painful, and we hear you on what seems to be very slow work on the FM 740 widening project. This is not a City project, but rather a state project. However, City Management stays in contact with TxDOT to urge and encourage progress on behalf of our community on this very […]

CONSTRUCTION NOTICE: TXDOT FM-740 SOUTH OVERLAY PROJECT

The contractor for the TXDOT FM-740 South Overlay Project, from the Smirl Drive/Laurence Drive intersection, south, towards Travis Ranch, is scheduled to begin roadway striping on Tuesday, October 13. The striping will take several days. Drivers should anticipate traffic delays during the installation of the roadway striping.

Updates on Upcoming TxDOT Projects

The construction start date for the FM-740 widening project from FM 1140 north to FM 1140 south is mid-July. Adverse weather delayed utility relocations, but that work is just about wrapped up. The contractor anticipates a completion date in the winter of 2017. The FM-3097 reconstruction project from Horizon Road to Tubbs in the City […]

City of Heath at Work in Your Neighborhood: Scenic Drive Paving Reconstruction

Paving reconstruction continues in the City along Scenic Drive near 600 and 404 Scenic Dr.  Construction is scheduled to begin on Friday, May 29 (weather permitting). Work is permitted between 7a.m. to 8p.m., Monday through Friday. The roadway will typically be constructed one-half at a time and will be reduced to one lane during construction. […]

Street Repairs To Start In The Ridge Subdivision

More streets are getting repaired under the City of Heath’s Capital Improvement Program! Next on the list are seven locations within The Ridge Subdivision. Construction is scheduled to begin Friday, May 8, weather permitting. Construction is allowed between the hours of 7 a.m. and 8 p.m. weekdays. The roadway will typically be constructed one-half at […]

Capital Improvement Program Roadway Repair Project- Shepherds Glen

PROJECT SCOPE:  The City project includes reconstruction of the intersection of Shepherds Glen Road and Stillwaters. The construction is scheduled to begin at on Monday, April 13, 2015 (weather permitting). Construction is allowed between 7:00 am to 8:00 pm, Monday through Friday. The roadway will typically be constructed one-half at a time and will be […]