FM 550 Construction Update for 09/27/18

The Contractor for the FM-550 TXDOT project plans to begin working to restore the culvert crossing, that was washed out last Saturday, September 22, back to normal conditions tomorrow (Friday September 28) and finish up on Saturday, September 29. FM-550 will be reduced to one-lane, with flaggers, during the repair work.

FM 549 Paving Update 08/22/18

Current schedule (as of August 22, 2018; weather dependent): FM-549- Thursday, August 30th and scheduled to take one day: Chip seal (surface before asphalt) FM-549, from the new Cain driveway on FM-549 to the bridge, then from the bridge to the FM-740 intersection. The roadway will be reduced to one lane during the chip seal […]

Construction Update: TXDOT FM-549 and FM-550 OVERLAY PROJECT

PROJECT SCOPE: UPDATED The TXDOT roadway improvement project includes the addition of 2-foot shoulders on FM-549 and FM-550 and the removal of the existing asphalt pavement and the installation of a new asphalt surface. The FM-549 portion of the project is from SH-205 to the FM-549/FM-550/FM-740 intersection. The FM-550 portion of the project is from […]

CONSTRUCTION NOTICE: Myers Road and Crisp Lane Project

PROJECT SCOPE: The City project includes reconstruction of Crisp Lane from Hubbard Drive to Myers Road and Myers Road from Crisp Lane to Terry Lane. The roadways are being reconstructed. The new roadways will be 20-foot wide concrete streets. The roadways will not have curb and gutters. The bids for construction were received on June […]

CONSTRUCTION NOTICE: TXDOT FM-549 and FM-550 OVERLAY PROJECT

PROJECT SCOPE: The TXDOT roadway improvement project includes the addition of 2-foot shoulders on FM-549 and FM-550 and the removal of the existing asphalt pavement and the installation of a new asphalt surface. The FM-549 portion of the project is from SH-205 to the FM-549/FM-550/FM-740 intersection. The FM-550 portion of the project is from SH-205 […]

CITY OF HEATH CAPITAL IMPROVEMENT PLAN PROGRESS

The Capital Improvement Plan continues to progress, providing upgrades and improvements to our City infrastructure. COMPLETED PROJECTS Dennis Bailey Drive/Rabbit Ridge Phase 1 (adjacent to Ridge Lakes subdivision) Rabbit Ridge and Horizon Rd. Extension (Adjacent to Cobblestone Subdivision) Shepherds Glen Force Main and Gravity Sewer Woodbridge Lift Station Country Club Drive Rehabilitation Amy Parks Driveway […]

TxDOT Construction Alert

Hubbard Drive, between Larry Drive and Smirl Drive, will be closed from 6 p.m., Friday, May 5, through 7 a.m. Monday, May 8, for roadway work related to the TXDOT FM-740 project. Traffic will be routed onto Larry Drive and Terry Lane. The intersection at Smirl Drive and FM-740 will be open except for the […]

FM 740 Construction Update

Weather permitting, the contractor for the TxDOT FM-740 project has informed City staff that paving will begin Monday morning, January 9. The paving will begin at the FM-740/FM-1140 intersection (City Hall) and continue to the FM-740/FM-550 intersection (Shell gas station). It is anticipated that it will take approximately seven days to complete this section, and […]

CIP Construction Update – Dennis Bailey and Rabbit Ridge

Project: The City is reconstructing a portion of Dennis Bailey and Rabbit Ridge. The project includes the reconstruction of Dennis Bailey from FM-549 to Rabbit Ridge and the section of Rabbit Ridge adjacent to the Ridge Lakes Addition (location map above). Start Date: The project has started. Completion Time: Estimated completion time is 7 months […]

Heath City Council Votes to Move Forward with Important Community Improvement Projects

The Heath City Council reviewed a Plan of Finance from the City’s financial advisor to fund close to $20 million in new Capital Improvement Projects and approved a Resolution Authorizing Publication of Notice of Intent to issue Combination Tax and Surplus Revenue Certificates of Obligation during its October 25 meeting. “As a result of the […]

CIP Project Update – Heath Drive between Yankee Creek Road and James Drive

Project: The City project includes reconstruction of a portion of  Heath Drive between Yankee Creek Road and James Drive (approximately 1200 feet) and two locations on Craig Drive (location map above). Start Date: The construction is scheduled to begin Tuesday, September 20, 2016 (weather permitting). Completion Time: Estimated completion date is the end of the […]

CIP Project Update – Terry Lane near Meadowview Road

Project: The City is reconstructing a portion of Terry Lane near Meadowview Road (location map above). Start Date: The project is scheduled to begin July 25, 2016 and is weather dependent. Completion Time: Approximately 4 weeks, weather dependent. Contractor Guidelines and Information: Construction is allowed between 7:00 am to 8:00 pm, Monday through Friday. The […]